We were engaged by the Client to investigate water ingress impacting several units within the complex.

Our investigation identified ponding water and multiple failures to the existing waterproof membrane system; including but not limited to debonding of laps, non-compliant terminations, general deterioration, and areas of water trapped beneath the membrane sheets.

After identifying the cause of the problem, we proceeded with preparation of specifications and DBP compliant regulated designs for the required remedial works; being rooftop re-waterproofing and associated work.

Landlay was engaged in the capacity of Superintendent alongside a reputable specialist remedial Building Practitioner to ensure successful delivery of the project.

Back to Projects